Revival Phase-2 Report

District : WEST GODAVARI
SNo.Scheme NameAyacut(in Acres)Admin Sanction Amount (Rs in Lakhs)Present stage of repairsNature Of RepairImageGis
12345678
1 Arulla700.0022.30Grounded and work is in ProgressCivil, Eletrical & Mechanical Works
2 Brahmanagudem1200.0052.28Grounded and work is in ProgressGravity main with RCC pipes
3 Gadidaboru –I125.0017.73Grounded and work is in ProgressCivil, Eletrical & Mechanical Works
4 Gadidaboru –II150.0016.96Grounded and work is in ProgressCivil, Eletrical & Mechanical Works
5 Nidadavole600.0032.39Completedconstruction of manhole chambers - 2 Nos. on intake pipe line
Gravity mains with PVC pipes
Supply and erection of brand new 30 HP HCF Pumpsets- 2 Nos
8 Pedatadepalli900.0026.81Grounded and work is in ProgressCivil, Eletrical & Mechanical Works
9 Polavaram750.0028.32CompletedCivil, Eletrical & Mechanical Works
10 Vegeswarampuram5840.00827.50CompletedConstruction of RCC Guide walls in main canal
Supply and erection of brand new 125 HP VT Pumpsets- 4 Nos.
Note: In Prakasam district Schemes under revival are renumbered to 84 against 108